Projects are completed based on approval submission date or criticality.

Only campus administrators may approve a change of priority for staff or faculty submitted projects.

Use the link below to open the schedule for planned and requested projects.

Project Planning and Progress (requires MS Excel)

Depending on the scale of any project, time is required to appropriately carry out the work. The chart below is a general guideline of how much time a project may require before completion.


Range of Duration for Projects UNDER $400,000

Process

Duration

Estimating and Scoping
1-6 Weeks
Architect and Engineer Selection (unless in-house design)
1-4 Weeks
Design and Specification
1-13 Weeks
Bidding and Award
2-8 Weeks
Construction, Occupancy and Closeout
4-23 Weeks

Range of Duration for Projects OVER $400,000

Process

Duration

Programming
4-12 Months
Architect and Engineer Selection
1-3 Months
Design and Specification
3-12 Months
Bidding and Award
2-3 Months
Construction, Occupancy and Closeout
3-36 Months